16. Gol Gohar Iron Ore Concentrate Line 4 Project

Electrical, Control and Instrumentation Systems Installation and Commissioning

Main Employer Gol Gohar Mining and Industrial Company

Employer Fakoor Sanat Tehran

Main Contractor Machine Sazi Vijeh

Execution Period 1400-01

Gol Gohar’s fourth iron concentrate production line (Polycom), with a production capacity of 2 million tons,

was commissioned in 1390. A quality-improvement and capacity-increase project for the concentrate

product was awarded in 1398 to Fakoor Sanat Engineering as an EPC contract. Rastak Pouya served as

contractor for installation and commissioning of the project’s electrical, control and instrumentation

systems.

16. پروژه خط چهارم کنسانتره سنگ آهن گل گهر

نصب و راه اندازی سیستم های برق، کنترل و ابزاردقیق

کارفرمای اصلی: شرکت معدنی صنعتی گل گهر

کارفرما: فکورصنعت تهران

پیمانکار اصلی: ماشین سازی ویژه

زمان اجرا: 01-1400

معرفی پروژه:

خط چهارم تولید کنسانتره آهن (پلی کام) گل گهر با ظرفیت تولید 2 میلیون تن، در سال 1390 به بهره برداری رسید. پروژه بهبود کیفیت محصول کنسانتره و افزایش ظرفیت تولید در سال 1398 به صورت EPC به شرکت مهندسی فکورصنعت واگذار شد.

شرکت رستاک پویا به عنوان پیمانکار، مسئولیت عملیات نصب و راه اندازی سیستم های برق، کنترل و ابزاردقیق پروژه را به عهده داشت.

Project dataاطلاعات پروژه

Clientکارفرما
Fakoor Sanat TehranFakoor Sanat Tehran
Locationموقعیت
Sirjanسیرجان
Yearسال
1400-011400-01
Portfolio categoryدسته‌بندی
Mineral Industriesصنایع معدنی
Scopeمحدوده
Cدر حال اجرا

Delivery scopeمحدوده تحویل

Execution Packageبسته اجرایی

  • اجرای برق و ابزاردقیقاجرای برق و ابزاردقیق