Kaveh 170 MW Solar Methanol Power Plant Projectنیروگاه 170 مگاواتی خورشیدی متانول کاوه

52. Kaveh Methanol 170 MW Solar Power Plant
Solar Power Plant Installation and 63 kV Transmission Line
Employer Kaveh Methanol
Status Completed
Construction of the 170 MW Kaveh Methanol solar power plant started in 1403 around Mamuniyeh, Saveh.
The first phase, with 30 MW capacity, was inaugurated and connected to the grid in Mordad 1404 by the President. Main equipment including panels, inverters and structures was supplied by the employer from China.
Rastak Pouya Engineering, as execution contractor, was responsible for installing equipment for 17.5 MW of
the plant and completed the work within three months to the employer’s satisfaction. Rastak Pouya also constructed the 63 kV transmission line connecting the plant to the grid.
52. نیروگاه 170 مگاواتی خورشیدی متانول کاوه
نیروگاه 170 مگاواتی
متانول کاوه
تکمیل شده
معرفی پروژه:
پروژه احداث نیروگاه 170 مگاواتی خورشیدی متانول کاوه در سال 1403 و در اطراف شهرستان مامونیه ساوه آغاز شد و فاز اول آن در مردادماه سال 1404 با ظرفیت 30 مگاوات توسط ریاست محترم جمهوری افتتاح و وارد شبکه شد.
تجهیزات اصلی نیروگاه شامل پانل، اینورتر، استراکچر و ... توسط کارفرما از چین تامین گردید.
شرکت مهندسی رستاک پویا به عنوان پیمانکار اجرایی، مسئولیت نصب تجهیزات 17.5 مگاوات از این نیروگاه را به عهده داشت
که این کار طی مدت 3 ماه با رضایت کارفرما انجام شد.
همچنین احداث خط انتقال 63 کیلوولت برای اتصال نیروگاه به شبکه توسط این شرکت انجام شد.
Project dataاطلاعات پروژه
- Clientکارفرما
- Kaveh MethanolKaveh Methanol
- Locationموقعیت
- Kaveh Methanolمتانول کاوه
- Yearسال
- Portfolio recordPortfolio record
- Portfolio categoryدستهبندی
- Solar Power Plantsنیروگاه خورشیدی
- Scopeمحدوده
- Cدر حال اجرا
Delivery scopeمحدوده تحویل
Execution Packageبسته اجرایی
- اجرااجرا
Project gallery